Completion of Phase I construction of the office building and factory workshop

post img
 
Phase I of the project, which commenced on the site handed over on December 16, 2022, was executed under contract and completed on November 30, 2023, by the winning construction company Impex Aurora S.R.L., under the management of director Szántó Péter. Haba Gellért, site supervisor (Cursor-Hafe S.R.L.), and architect Gergely Attila (Vallum S.R.L.) continuously monitored, verified, and coordinated the project together with the contractor and the client. We thank all employees and subcontractors of the three companies for their help and hard work!

Completed construction works up to November 30, 2023, for Phase I, in percentages %:
Total completed work: 100%
(Contracted amount for Phase I / amount of work completed by November 30, 2023)
Record of completed works by type of work:
 

Office Building Construction
Structural works - substructure: 100%
Structural works - superstructure: 100%
Masonry and insulation: 100%
Exterior works: 100%
Interior works: 100%
Interior electrical installation: 100%
Low-voltage data network: 100%
Fire alarm system: 100%
Intrusion alarm system: 100%
Access control system: 100%
Surveillance system - camera network: 100%
Building Management System (BMS) preparation: 100%
Ventilation system: 100%
Heating system: 100%
Interior plumbing and sanitary installations: 100%
Interior sewage system: 100%
Exterior water system: 100%
Exterior sewage system: 100%
Procurement of equipment and installations for the heating system: 100%
Procurement of equipment and installations for the ventilation system: 100%
 
Workshop Building Construction
Structural works - substructure: 100%
Structural works - superstructure: 100%
Masonry and insulation: 100%
Exterior works: 100%
Interior works: 100%
Interior electrical installation: 100%
Low-voltage data network: 100%
Fire alarm system: 100%
Intrusion alarm system: 100%
Access control system: 100%
Surveillance system - camera network: 100%
Building Management System (BMS) preparation: 100%
 
 

 